Accept Project as complete and authorize the Clerk of the Board to execute Notice of Completion of Contract and Acceptance of Work on Contract No. 24-20, SCC Parks and Recreation Silver Creek Project. Contractor - SC Builders, Inc.
The document is a Notice of Completion for the SCC Parks and Recreation Silver Creek Project, addressed to the Board of Supervisors. It recommends accepting the project as complete and authorizing the Clerk of the Board to execute the Notice of Completion of Contract No. 24-20 with SC Builders, Inc. The project was funded through two sources, totaling $14,123,455 in completed work. The document outlines the contract history, reasons for the recommendation, and the implications of the action.
Key points
The project is for the SCC Parks and Recreation Silver Creek Project.
The contractor is SC Builders, Inc.
Total cost of completed work is $14,123,455.
The project involved 91 change orders for various construction needs.
The recommended action allows the Department to close out the project contract.
There is no impact on the County General Fund from this action.
The project was designed to accommodate administrative and operational needs of the Parks Department.
Limitations
The document contains placeholders and unresolved sections, such as the date and specific details about attachments.
The text indicates a specific date of June 23, 2026, which may not be the actual date of the document's creation or approval.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 4,919 chars
County of Santa Clara Parks and Recreation Department 129203 DATE: June 23, 2026 TO: Board of Supervisors FROM: Todd Lofgren, Director, Parks and Recreation Department SUBJECT: Notice of Completion for SCC Parks and Recreation Silver Creek Project RECOMMENDED ACTION Accept Project as complete and authorize the Clerk of the Board to execute Notice of Completion of Contract and Acceptance of Work on Contract No. 24-20, SCC Parks and Recreation Silver Creek Project. Contractor - SC Builders, Inc. FISCAL IMPLICATIONS There is no impact to the County General Fund as a result of the recommended action. The contract for the SCC Parks and Recreation Silver Creek Project was funded from two funding sources: $8,451,535 was provided from Fund 0050, General Capital Improvement Fund (Capital Project #263-24004) to support the capital improvements, and $5,671,920 was provided by the Parks Charter Fund to support the tenant improvements. CONTRACT HISTORY On September 10, 2024, the Board of Supervisors awarded the contract to SC Builders, Inc. in the amount of $11,428,000 and authorized a Supplemental Work Allowance (SWA) of $1,714,200 and a construction duration of 275 to 315 calendar days...
This document is a Notice of Completion of Contract and Acceptance of Work for the Silver Creek Park Admin Building project, executed by the County of Santa Clara and SC Builders, Inc. The work was completed and accepted on June 23, 2026. The contract number is 24-20, and the surety for the contract was Fidelity and Deposit Company of Maryland. The document is signed by Curtis Boone, Clerk of the Board of Supervisors.
Key points
Project: Silver Creek Park Admin Building
Contractor: SC Builders, Inc.
Contract Number: 24-20
Completion and acceptance date: June 23, 2026
Surety: Fidelity and Deposit Company of Maryland
Clerk of the Board: Curtis Boone
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 2,608 chars
County of Santa Clara Parks and Recreation Department 5965 Silver Creek Valley Road San Jose, California 95138 (408) 355-2200 FAX (408) 355-2290 Reservations (408) 355-2201 www.parkhere.org NOTICE OF COMPLETION OF CONTRACT AND ACCEPTANCE OF WORK NOTICE IS HEREBY GIVEN by order of the Board of Supervisors of the County of Santa Clara, State of California, pursuant to State law, that the work to be performed under the contract heretofore made and executed by and between the County of Santa Clara, as owner herein, and: SC Builders, Inc. 910 Thompson Place, Sunnyvale, CA 94085 as Contractor therein, bearing the date: September 10, 2024 for construction of: Silver Creek Park Admin Building Contract No. 24-20 and appurtenant facilities upon lands of said County known as: SCC Parks and Recreation Silver Creek Project – 5965 Silver Creek Valley Road, San Jose, CA 95138 situated in the County of Santa Clara, State of California, was completed by the Contractor, and the work was accepted by the said Board on behalf of said County on: June 23, 2026 Upon said contract, Fidelity and Deposit Company of Maryland - Bond No. 9460763 was surety on the bond given by said: SC Builders, Inc. the...
03
94.2 KB
SCB - Final Completion Certification_Silver Creek Project
This letter certifies the completion of all construction work for the SCC Parks & Recreation Admin Facility project as per the contract. Final programming and commissioning for the Security System will be completed by April 30, 2026, and retention will be held until this is complete. All punch list items are complete, and a request is made to release the final retention payment.
Key points
Final Completion Certificate for SCC Parks & Recreation Admin Facility project.
All construction work has been completed as per the contract.
Final programming and commissioning for the Security System will be completed by April 30, 2026.
Retention will be held until the Security System is complete.
All punch list items are complete.
Request to release final retention payment.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 829 chars
April 22, 2026 Jorge Fernandez 5965 Silver Creek Valley Road San Jose, CA 95138 Re: SCC Parks & Recrea!on Admin Facility Project No. 124111 FINAL COMPLETION CERTIFICATE This le+er is to cer!fy that all construc!on work for the SCC Parks & Recrea!on Admin Facility project has been completed as per the contract. Some final programming and commissioning for the Security System will be completed by April 30, 2026, and reten!on will be held from MDC un!l this is complete. All punch list items are complete. Please release final reten!on payment. Regards, Joe Ascolese Project Execu!ve SC Builders, Inc. 910 Thompson Place Sunnyvale, CA 94085 408.328.0688 | www.scbuildersinc.com License No. 767196 B 910 Thompson Place, Sunnyvale, CA 94085 408.328.0688 | www.scbuildersinc.com | Lic # 767196 B Silicon Valley | San Francisco
This document is a guarantee/warranty from SC Builders, Inc. for the work completed at the SCC - Parks & Rec Admin Facility project. It states that the work has been completed according to specifications and contract documents. SC Builders, Inc. agrees to repair or replace any defective work within one year from the date of acceptance by the Owner, with the exception of ordinary wear and tear and unusual abuse or neglect. If SC Builders, Inc. fails to comply with repair requests within ten days of written notification, the Owner is authorized to have the work repaired at SC Builders, Inc.'s expense.
Key points
Guarantee/Warranty for work at SCC - Parks & Rec Admin Facility.
Work completed in accordance with specifications and contract documents.
Defective work will be repaired or replaced within one year from acceptance date.
Owner must notify SC Builders, Inc. in writing of defects.
SC Builders, Inc. will cover costs if they fail to repair within ten days of notification.
Limitations
The acceptance date is stated as October 17, 2025, which may be an error as it is in the future.
The document does not specify the exact date of completion of the work.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 1,262 chars
GUARANTEE / WARRANTY FO R SC BUILDERS, INC. Guarantee/Warranty for the work, which we have provided at the SCC - Parks&Rec Admin Facility (124111) project has been completed in accordance with the Specifications and the other Contract Documents. We agree to repair or replace any or all of our work, together with any other adjacent work which may be displaced by so doing, that may prove to be defective in its workmanship or material within a period of one year(s) from the date of acceptance October 17, 2025 of the above named project by the Owner; and we also agree to repair any and all damages resulting from such defects, all without any expense to the Owner, ordinary wear and tear and unusual abuse or neglect excepted. In the event of our failure to comply with the above mentioned conditions within ten (10) DAYS AFTER BEING NOTIFIED IN WRITING BY THE Owner, we collectively or separately do hereby authorize the Owner to proceed to have such defective work repaired or replaced and made good at our expense, and we will honor and pay the costs and charges therefore upon demand. SC BUILDERS, INC. Company Signature Date 910 Thompson Place, Sunnyvale, CA 94085 408.328.0688...