Change Order No. 1 Project No. 263-CP21003-1
Change Order No. 1 pertains to the OCH and SLRH Security Replacement project, under Project No. 263-CP21003-1. The contractor, FE Controls Corporation, is directed to make changes due to unforeseen conditions discovered during construction, including asbestos and inaccessible electrical panels. The change order includes multiple proposed change order numbers and outlines the terms and conditions for compensation and additional work. The total adjustment in the Contract Sum is $787,400.05, which is intended to cover all costs associated with the changes through August 25, 2026. The completion date is extended by 911 days to May 30, 2027.
Key points
- Project Title: OCH and SLRH Security Replacement
- Contractor: FE Controls Corporation
- Change Order covers multiple proposed change orders (01, 02, 03, etc.)
- Total adjustment in Contract Sum: $787,400.05
- Completion date extended to May 30, 2027
- Includes terms for indemnity, waiver of claims, and integration clause
Limitations
- The text contains unresolved placeholders and formatting artifacts.
- Specific details regarding the proposed change orders are not fully elaborated.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.