Consider recommendations relating to the County Sanitation District 2-3 Structural Defect Repair Project – Phase 2. California Environmental Quality Act (CEQA): Exempt from CEQA pursuant to 15301(b), 15302 (c), and 15303 (d) of the CEQA Guidelines.

Environment & Sustainability Board of Supervisors
2 Documents on file 22.2 MB · 2 extracted · 2 AI summaries
File
SCC-129876
Type
Unknown
Status
Unknown
Requester
Unknown
Introduced
Unknown
Last synced
20 Aug 2026 · 05:45

The papers

01 19.8 MB

CSD 2-3 Plans Structural Defect Repair Project Phase 2

19.8 MB Extracted AI Summary
file Unknown sha ece7bac454d7 source Open source document ↗
Generated summary AI-assisted

The document outlines a structural defect repair project for various pipe segments, detailing specific repairs needed for each segment, including the type of pipe, length of replacement, and repair depths. It includes both point repairs and pipe bursting operations across multiple locations, with specific references to defects that need to be fixed.

Key points
  • The project involves point repairs and pipe bursting for various segments of VCP and PVC pipes.
  • Each repair specifies the length of pipe to be replaced, the type of pipe, and the depth of repair.
  • Defects to be fixed are categorized with identifiers such as (B), (BSV), (FM), and (MWLS).
  • The document includes details for sewer extensions on Chula Vista Ave and Chula Vista Ct.
Limitations
  • The text appears to contain formatting issues and may not be complete.
  • Some sections contain unresolved placeholders or missing information, such as specific identifiers and measurements.

Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.

Extracted text preview · 11,084 chars
            R                       SHEET NO. LOCATION NO. PIPE ID C-1 1 1470 C-1 2 1471 C-2 3 1698 C-2 4 2121 C-3 5 1568 C-3 C-4 6 7 1631 1490 C-4 8 1489 C-5 9 1075 C-6 10 1788 C-6 11 1786 C-7 12 11331 C-8 13 11011 C-9 14 1537 C-9 15 1330 C-10 16 1449 C-11 17 2177 C-12 18 - C-13 19 - PIPE SEGMENT REPAIR SCOPES 1 - POINT REPAIR - REMOVE AND REPLACE 6' OF 6" VCP WITH 6' OF 6" PVC SDR26 FROM 305 TO 311 FEET FROM SSHM-1470-724. FIX (B) DEFECT. REPAIR DEPTH IS APPROXIMATELY ~ 7.7'. 2 - POINT REAPIR - REMOVE AND REPLACE 11' OF 6" VCP WITH 11' OF 6" PVC SDR26 FROM 553 TO 564 FEET FROM SSMH-1470-724. FIX (B/BSV) DEFECTS. REPAIR DEPTH IS APPROXIMATELY ~ 8.1'. 3 - POINT REPAIR - REMOVE AND REPLACE 7' OF 6" VCP WITH 7' OF 6" PVC SDR26 FROM 155 TO 162 FEET FROM SSMH-1470-725. REINSTATE ONE (1) 6"X4" WYE CONNECTION AT STA 20+24.04. FIX (FM) DEFECT. REPAIR DEPTH IS APPROXIMATELY ~ 7.2'. 4 - POINT REPAIR - REMOVE AND REPLACE 6' OF 6" VCP WITH 6' OF 6" PVC SDR26 FROM 256 TO 262 FEET FROM SSMH 1470-725. FIX (B) DEFECT. REPAIR DEPTH IS APPROXIMATELY ~...
02 2.43 MB

CSD 2-3 Specifications Structural Defect Repair Project Phase 2

2.43 MB Extracted AI Summary
file Unknown sha cba0c7af7167 source Open source document ↗
Generated summary AI-assisted

The document outlines the specifications for the Structural Defect Repair Project Phase 2 for the County Sanitation District No. 2-3. It includes details about the project, bid submission requirements, and the scope of work, which involves various sewer mainline repairs and replacements. The bid due date is set for September 17, 2026, and the project is expected to be completed within 65 working days from the Notice to Proceed.

Key points
  • Project Name: Structural Defect Repair Project Phase 2
  • Prepared for County Sanitation District No. 2-3
  • Bid Specifications Dated: July 08, 2026
  • Bid Due Date: September 17, 2026, before 2:00 PM
  • Scope includes repairs and replacements of sanitary sewer mains and lateral connections at multiple locations.
  • Contractor must be registered with the County Sanitation District and the Department of Industrial Relations.
  • Bids must be submitted under seal and will be returned unopened if received late.
  • Project completion is required within 65 working days from the Notice to Proceed.
Limitations
  • The document contains placeholders and incomplete sections, such as specific details about the bid forms and other documents.
  • Some sections of the text are truncated, leading to missing information.

Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.

Extracted text preview · 465,580 chars
Docusign Envelope ID: A2D11AE2-0C2F-8E93-835E-1B745FEB81E8 STRUCTURAL DEFECT REPAIR PROJECT PHASE 2 CONTRACT SPECIFICATIONS FOR: COUNTY SANITATION DISTRICT NO. 2-3 PREPARED BY: 20863 Stevens Creek Boulevard, Suite 100 Cupertino, California 95014 (408) 253-7071 APPROVED BY: _________________________________ _ Harry Freitas, P.E., Director Roads and Airports Department County of Santa Clara ________________________________ Benjamin T. Porter, P.E. District Manager-Engineer County Sanitation District No. 2 3 Bid Specifications Dated: July 08, 2026 Bid Due Date on Thursday, September 17, 2026 before 2:00 PM County Sanitation District 2-3 STRUCTURAL DEFECT REPAIR PROJECT – PHASE 2 STRUCTURAL DEFECT REPAIR PROJECT – PHASE 2 PROFESSIONAL ENGINEER’S CERTIFICATION FOR ESTEBAN DELGADILLO, PE Specifications Dated: July 08, 2026 Bid Due Date on Thursday, September 17, 2026 before 2:00 PM (PST) _________________________ Esteban M Delgadillo, PE C. # 90449 Expires September 30, 2027 Mark Thomas 20863 Stevens Creek Blvd., #100 Cupertino, CA 95014 All of the Technical Specifications for the above referenced project were prepared under my direction and supervision. 0|Page County Sanitation...